Ertis Hydrometallurgical Plant (Ertis POX)

Project Description:

The Ertis Hydrometallurgical Plant is a state-of-the-art pressure oxidation (POX) facility under development by Solidcore Resources plc (formerly Polymetal International). Located within the Pavlodar Special Economic Zone in Kazakhstan, the plant is designed to process refractory gold concentrates, which make up over 80% of the company’s mineral reserves.

The Ertis POX facility will utilize cutting-edge processing technologies to produce high-purity Dore bars containing up to 98% gold. The project plays a strategic role in Solidcore’s vertical integration efforts, aiming to reduce reliance on third-party processing, increase operational efficiency, and enhance value retention within Kazakhstan.

Once operational, Ertis POX will be among the most advanced gold concentrate processing plants in Central Asia and will be the first of its kind at this scale in Kazakhstan. The facility is designed to support long-term sustainable operations in line with international environmental and safety standards.

Current Status:

As of April 2025, the project has received initial construction permits, and preparatory work is underway. The delivery of the autoclave is scheduled, with full-scale construction expected to commence in the second half of 2025.

Start Date: October 2024

End Date: First half of 2028

Investment Volume (in mln USD):

Approximately $978 million

Location:

Pavlodar, Special Economic Zone (SEZ) "Pavlodar," Kazakhstan

Involved Companies:

1. Solidcore Resources plc (former Polymetal International)

  • Role: Project owner, developer, and operator

  • Address: 1306 Office, 13th floor, 10 Dinmukhamed Qonayev Street 010000, Esil District, Astana, Kazakhstan

  • Phone: +7.7172.476.655 / Solidcore Eurasia LLC: +7.717.261.0222

  • Email: pme@solidcore-resources.kz

  • Web: https://www.solidcore-resources.com/en/

2. Hatch Inc.

  • Role: Engineering and procurement contractor

  • Address: Global Delivery Centre Sheridan Science & Technology Park 2800 Speakman Drive Mississauga Ontario L5K 2R7 Canada

  • Address: Sheridan Science & Technology Park 2699 Speakman Drive Mississauga Ontario L5K 1B1 Canada

  • Phone: +1 905 855 7600/ +1 905 855 7600

  • Web: https://www.hatch.com/en

  • LinkedIn

3. COEK Engineering (Belgium)

  • Role: Equipment manufacturer

  • Address: Liessel 13 2440 Geel / Vaartstraat 27 3600 Genk

  • Phone: +32 14 58 83 40 / + 32 89 35 81 33

  • Email: coek@coek.be

  • Web: https://www.coek.be/

4. Bai Tau Minerals (BTM)

  • Role: Strategic exploration partner

  • Address: Kazakhstan, Almaty, 10/1 Yelebekov Street, 3rd floor

  • Email: info@baitauminerals.com

  • Web: https://baitauminerals.com/en

Key People and Contact Details:

1. Solidcore Resources plc

Name: Амангельды Калеев

Position: Project Director - ТОО «Solidcore Eurasia»

Name: Igor Shauro

Position: Project manager

Name: Bakhyt B

Position: Renewable. Project and business development manager.

2. Hatch Inc

Name: Kendrick Tang

Position: Global Director - Rail & Supply Chain

Name: Jeanine Chown

Position: Project Procurement Manager

Name: Eric Murakami

Position: Global Director, HR Operations & Technology at Hatch

Email: eric.murakami@hatch.com

3. COEK Engineering

Name: Koen Van Looke

Position: CEO

Email: koen.van.looke@coek.be

Name: Jordy Ceulemans

Position: Project Engineer

4.Bai Tau Minerals

Name: Георгий Джеджея

Position: Lead Geologist

Name: Daniyar Zhurekbayev

Position: Investment Manager

Email: daniyar.zhurekbayev@gmail.com

Other Important Details:

  • Capacity: Designed to process up to 300,000 tonnes of concentrate per year.

  • Employment Impact: Expected to create approximately 500 permanent jobs and over 1,000 jobs during the construction phase.

  • Environmental Considerations: The facility will incorporate a Cyanide Management System and pursue certification under the Cyanide Code upon commissioning.

Sources: