PROJECT DESCRIPTION
This project involves the construction of a 50 MW combined-cycle (steam + gas) power plant in the village of Auliekol, Zhambyl District, Zhambyl Region, Kazakhstan. It is being developed by GES Myrzatai LLP with an investment of US$ 60 million. The project will be implemented in two phases: the first phase is 50 MW, and the second will expand capacity by another 150 MW, bringing the total to 200 MW. Preparatory work has already been completed, including securing a 7-hectare land plot, engineering and hydrogeological surveys, drilling a 185-meter well, selecting a general contractor, and obtaining technical conditions for a gas connection. App... Read more
Involved Companies & Contacts
INVOLVED COMPANIES & CONTACTS
COMPANY 1 INFO
COMPANY:
░░░░░░░░░░░░░░
ROLE:
░░░░░░░░░░░░░░░░░░░░░░░
ADDRESS:
░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░
PHONE:
░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░
EMAIL:
5. party1CompanyEmailText
WEBSITE:
6. party1CompanyWebsiteText
OTHER LINKS:
7. party1CompanyWebsiteText
KEY CONTACTS
NAME:
░░░░░░░░░░
POSITION:
░░░░░░
PHONE:
party1Contact1PhoneText
EMAIL:
party1Contact1EmailText
LINK:
party1Contact1LinkText
NAME:
party1Contact2NameText
POSITION:
party1Contact2PositionText
PHONE:
party1Contact2PhoneText
EMAIL:
party1Contact2EmailText
LINK:
party1Contact2LinkText
Location
Locations shown on the map are for indicative purposes and may vary from actual locations.
Other important details
GES Myrzatai LLP, founded in 2020, is owned by Serzhan Alimov (directly) and Kazakh Nantian Energy Limited, which in turn is owned by Auspicious Fly International Trade Co., Ltd. (Hong Kong), making part of the company foreign‑owned.
The project was publicly announced by Kazakh Invest during a press event.
Akim of Zhambyl Region attended the groundbreaking.
According to the project manager- Hou Chuanqun, all major preparatory work (surveys, well drilling, land acquisition) is already complete.