300 MW Solar Power Plant Turkistan Region (Updated)

Potato Processing Complex.jpg
Photo Sources: www.samruk-energy.kz

PROJECT ID

172025176

SECTOR

Energy & Power Generation, Renewable Energy

PROJECT PHASE

Procurement & Construction

LOCATION

Sauran, Kazakhstan

START DATE

12/15/2025

END DATE

9/1/2026

INVESTMENT VALUE

$ 320 M

Active

gifyyyyy.gif

Verified

Last Updated: 26 May 2026

Publication: 15 December 2025

PROJECT DESCRIPTION

The project involves the construction of a utility-scale solar photovoltaic power plant in the Sauran District of Turkistan Region, Kazakhstan. The officially stated installed capacity is 300 MW AC, with an energy storage system included in the project scope. According to Samruk-Energy, the project configuration is 300 MW solar PV with a 90 MW / 360 MWh energy storage system, while the environmental screening document refers to a 95 MW / 380 MWh storage system; both figures come from official/project-related documents, so the difference should be treated as a document-level discrepancy.   The project includes the construction of a 2... Read more

Involved Companies & Contacts

INVOLVED COMPANIES & CONTACTS

COMPANY 1 INFO

COMPANY:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

ROLE:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

ADDRESS:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

PHONE:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

EMAIL:

░░░░░░░░░░░░░░░░░░

WEBSITE:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

OTHER LINKS:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

KEY CONTACTS

NAME:

░░░░░░░░░░░░░░░

POSITION:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

PHONE:

░░░░░░░░░░░░░░░░

EMAIL:

░░░░░░░░░░░░░░░░░░░░░░░░░

LINK:

party1Contact1LinkText

NAME:

░░░░░░░░░░░░░░

POSITION:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

PHONE:

░░░░░░░░░░░░░░░░

EMAIL:

░░░░░░░░░░░░░░░░░░░░░░░░░░░

LINK:

party1Contact2LinkText

COMPANY 2 INFO

COMPANY:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

ROLE:

░░░░░░░░░░░░░░░░░░░░░░░

ADDRESS:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

PHONE:

░░░░░░░░░░░░

EMAIL:

5. party1CompanyEmailText

WEBSITE:

░░░░░░░░░░░░░░░░░░░░

OTHER LINKS:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

KEY CONTACTS

NAME:

party1Contact1NameText

POSITION:

party1Contact1PositionText

PHONE:

party1Contact1PhoneText

EMAIL:

party1Contact1EmailText

LINK:

party1Contact1LinkText

NAME:

party1Contact2NameText

POSITION:

party1Contact2PositionText

PHONE:

party1Contact2PhoneText

EMAIL:

party1Contact2EmailText

LINK:

party1Contact2LinkText

COMPANY 3 INFO

COMPANY:

░░░░░░░░░░░░░░░░░

ROLE:

░░░░░░░░░░░░░░░░░░░░░░░

ADDRESS:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

PHONE:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

EMAIL:

░░░░░░░░░░░░░░░░░░░

WEBSITE:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

OTHER LINKS:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

KEY CONTACTS

NAME:

party1Contact1NameText

POSITION:

party1Contact1PositionText

PHONE:

party1Contact1PhoneText

EMAIL:

party1Contact1EmailText

LINK:

party1Contact1LinkText

NAME:

party1Contact2NameText

POSITION:

party1Contact2PositionText

PHONE:

party1Contact2PhoneText

EMAIL:

party1Contact2EmailText

LINK:

party1Contact2LinkText

COMPANY 4 INFO

COMPANY:

░░░░░░░░░░░░░░░░░░░░

ROLE:

░░░░░░░░░░░░░░

ADDRESS:

░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░

PHONE:

░░░░░░░░░░░░░░

EMAIL:

░░░░░░░░░░░░░░░

WEBSITE:

6. party1CompanyWebsiteText

OTHER LINKS:

7. party1CompanyWebsiteText

KEY CONTACTS

NAME:

░░░░░░░░░

POSITION:

░░░░░░

PHONE:

party1Contact1PhoneText

EMAIL:

party1Contact1EmailText

LINK:

party1Contact1LinkText

NAME:

party1Contact2NameText

POSITION:

party1Contact2PositionText

PHONE:

party1Contact2PhoneText

EMAIL:

party1Contact2EmailText

LINK:

party1Contact2LinkText

Location

Locations shown on the map are for indicative purposes and may vary from actual locations.

Other important details

  • On July 21, 2025, Qazaq Green Power PLC, together with Dutch Green Power Investment B.V., established the legal entity Sauran Solar Power LLP, in which the public company Qazaq Green Power PLC holds a 30% equity stake. The remaining 70% ownership interest belongs to Dutch Green Power Investment B.V.

  • Dutch Green Power Investment B.V. is listed in Dutch registry-derived sources under the ownership/management chain involving China Energy Overseas Investment (Hong Kong) Co., Limited and Dutch Future Investments B.V.

  • The project’s material requirements are significant and include 581,360 PV modules, 5,790 support structures, 72 km of 35 kV collector lines, 2 main transformers, and a large-scale BESS package.

  • The environmental document lists 1,192 tonnes of reinforcing steel and concrete volume stated as 3.5871 × 10,000 m³, which equals approximately 35,871 m³ if the document’s unit format is interpreted literally.

  • The document also lists earthworks / excavation as 142.2908 × 10,000 m³, equal to approximately 1,422,908 m³ under the same literal unit interpretation.

  • The project will require temporary construction facilities, including around 1,200 m² of temporary residential/office premises and around 2,000 m² of temporary processing/storage facilities.

  • Water supply for the construction stage is planned as delivered water: 4,320 m³/year for drinking/domestic needs and 240 m³/year for technical water used for dust suppression.

  • The environmental screening conclusion states that mandatory full environmental impact assessment is not required, and the project initiator must submit an environmental impact declaration to the relevant local executive body.

  • Public discussions were held from 23 September 2025 to 29 September 2025.

  • Samruk-Energy’s project page lists the signing of a power purchase agreement with the Renewable Energy Financial Settlement Center on 16 June 2025 and the signing of an investment agreement and power purchase agreement with Sauran Solar Power LLP on 2 September 2025.